2018 Street & Utility Improvements (2018-101)

Project Description

Scope of work includes total replacement of approximately 6,450 linear feet of sanitary sewer, water main and storm sewer, future conduit for fiber optic and street and sidewalk reconstruction in the following neighborhoods:

  • Redwood Drive, Circle, and Court
  • Keller Lake Drive
  • Apple Valley 12th Addition (Rome Drive and Court, Lowell Drive and Hopewell Lane)


Work has been completed.
Due to the late season finish, the contractor is aware that there will be warranty work to address in the spring. This work includes, but is not limited to, cracked sidewalks, driveways, curb, as well as sod and trees if needed.